The School Project in Douar-Ait-Abdi

The small Berber village Douar-Ait-Abdi is around two hours drive from Marrakech. Five years ago the village got a school. The school has around 50 boys and girls aged 7-13. There are two teachers for all students. The school day is divided into two different periods between eight in the morning and six in the evening.  The village is very poor and the school is in a bad shape, lacking basic things such as electricity, toilet, playing ground etc.  Riad Touareg Badie has initiated a socio-pedagogical project to support the inhabitants of the village in their efforts to give the children a better school with regard to the infra-structure as well as the pedagogical resources. 

To the left the two interconnected class rooms and the school yard before it was restored, and to the right some of the students in one of the class rooms before restoration. 

 

 

 

Restoration of the school

In cooperation with the village's local association for developing the village, the Riad Touareg Badie's school project has defined some basic tasks in developing the school. All guests and friends of the Riad Touareg Badie are invited to give a contribution, small or large. The main tasks in developing the school and basic pedagogical requisites are described below. In 2009 the renovation of the school started with economic support from the guests of Riad Touareg Badie  and a project conducted by students on the IB Diploma Programme at Katedralskolan in Lund, lead by Birgitta Roupé.

The economic support coordinated by our school project started in 2008. This money has been directly invested in the school according to a plan for material and pedagogical restoration presented below. This plan was developed by the owner of Riad Touareg Badie, Pär Nygren, based on observations and information trough interviews with school children, teachers, parents and other inhabitants in the village and in collaboration with the local association for developing the village. The responsibility for the restoration work is the president of the local village association for Douar-Ait-Abdi, together with the secretary of this  association. In 2009  the local authorities for the municipality gave the permission to start the restoration work at the school according to the proposed plan from our school project.

After an electrician and a represents from a local small building company had inspected the school, the association for the village represented by the secretary of the local association, Omar Aatabi, collected information about the detailed prices for the work planned by the school project.  The plan  for the work was in 2009 outlined as in the table below. The local election was held on the 25.6.09 and the new board of the association had a meeting directly after this election. On this meeting the plan shown in the table below was confirmed and the work started at 24.10.09 in accordance with the plan below.

At the time for the start of the school project, the roof was leaking and the school was without electricity. The conditions for teaching and learning in both class rooms was very bad in the cold seasons. Down to the left a picture of one of the class rooms reveals its bad condition of the walls and the windows before restoration.

The picture to the right below shows a ruin beside the school. The plan is to restore this house to a study room and a library.

The restoration work has given important results as can be seen on the newly taken pictures of the school and the classrooms.

 

 

 

 Pictures of the school in mars 2010

 

Electricity is connected, there is a new roof, new windows, the walls are painted in- and outside and the school yard is being prepared to give the childfren opportunity to play outside.  For overview of the tasks in the restoration work and of what is accomplished and stil remains, see the updated plan below.

 

Plan for the school project (updated 07.03.2010)

Phase 1 : basic tasks I  (24.10.- 14.11.09)
Financed by external support to the school project and earlier savings by the local association

 

Type of work

Planned costs

Date planned finished

Date actually finished

Comments

 1

Connect electricity to the two school buildnings.
Registration and connection
Meeter:
Material (boxes, outlets, cables etc)
Work

 6.010 dh

 14.11.09

10.12.09

 

2

New roof of two school buildings (stone), repair roof inside, painting of all walls outside and inside. Material and work

7.000 dh

14.11.09

01.12.09

 

3

New windows in both classrooms. Material and work

4.500 dh

14.11.09

10.12.09

 

Total costs

17.600 dh

 

 

 

Phase 2: Basic tasks II ( 24.10 – 14.11.09)
Financing plan:  future external support to the school project, future savings by the local association and support from the local and central school authorities

4

Installation of heaters in the class rooms (before winter time)
material and work

1500 dh

15.08.2010

 

 

6

Building of a two separate toilets for boys and girls. Material and work.

14.000 dh

10.06.2010

 

started

7

Building of a wall around the school area and a entrance to the school area
Material and work (free work by the village inhabitants)

15.000 dh

10.06.2010

 

started

8

1 computor with pedagogical dvd-program

3.000 dh

15.08.2010

 

 

9

Preparation of the school area in order that the children can use it for play

13.000 dh

10.06.2010

 

started, almost finnished

Total costs phase 2

46.500 dh

 

 

 

Phase 3: Extra tasks ( 1.5.10 – 1.8.2010)
Financing plan:  future external support to the school project and future savings by the local association

 

 

 

 

 

 

10

Reparing the old house (ruin) and restaurate it into a study room for children and library for books and as a meeting place for teachers and the families from village

15.000 dh

1.5 – 1.8.10

 

 

11

Installation of internet in school and the new study room.

?

1.8.10

 

 

 

 

Give your contribution!

The contributions to the project is transferred directly to the bank account for the local association for the village: Bank: Ait Ourir centre, Marrakech; Account no 6313714u651; RIB: 225454006313714651012178;  Swift code: CNCA MAMR.

The transfers must be marked “Riad Touareg-Badie School Project for DOUAR-AIT-ABDI” in order to be registered as a contribution to the project.

Also notify the staff of Riad Touareg Badie by e-mail (riad-touareg@riad-touareg.com) with information of sum and name of contributor.

The results of the work will continuously be published on this website.  Names of contributors are also published here - see below!
 

Contributors to the Riad Touareg Badie School Project so far

Ole Dreier, Dorte Bukh, Per Christian Ellefsen, Ana Soler, Harald Solem, Marcus Nygren, Brunjylf Hangaard, Anne Britt Hangaard, Birgitta Roupé, Sigrun Skranes, Pär Nygren, Janne Skranes, Rolf Rønning, Liv Solheim, Bente Fauske, Stig Ove Fossum, Minna Fagerstedt, Kalle Fransson, Torhild Engvik, Julia Brox Skranes, Johanne Brox Skranes, Jostein Skranes Brox, Driss Molay, Stian Langeland and the students on the IB Diploma Programme at Katedralsskolan in Lund, Sweden, Birte N. Borrevik, Grete Skjaastad, Gordon Harris.
 

 


 